Coventry Crossing

        Construction Progress Photos

 

                  June/July, 2008

 

   June/July, 2008

6-9-2008
Back side of building one.

 

  June/July, 2008

6-9-2008
F D C connecting on the back
side of the buildings.

 

  June/July, 2008

6-9-2008
Dumpster enclosure behind building one.

 

  June/July, 2008

6-9-2008 Fire hydrant next to main driveway.

 

  June/July, 2008

6-9-2008 Left end of building one.

 

  June/July, 2008

6-9-2008 Masonry going on dumpster
pad behind building two.

 

  June/July, 2008

6-9-2008 Masonry going on on dumpster
pad behind building one.

 

  June/July, 2008

6-9-2008 Right front corner of building one.

 

  June/July, 2008

6-9-2008 Running water line down Farrow Parkway.

 

  June/July, 2008

6-9-2008 Transformer Pad.

 

  June/July, 2008

6-9-2008 Walk between both building.

 

   June/July, 2008

6-12-2008
Duct and curb for exhaust fan.

 

   June/July, 2008

6-10-2008 Water tie-in.

 

   June/July, 2008

6-12-2008 Gas line.

 

   June/July, 2008

6-12-2008 Restroom exhaust fan.

 

   June/July, 2008

6-12-2008 Restroom framing on building one.

 

   June/July, 2008

6-12-2008 Riser room.

 

   June/July, 2008

6-12-2008 Unit A-2.

 

   June/July, 2008

6-12-2008 Unit A-7.

 

   June/July, 2008

6-12-2008 Unit B-7.

 

   June/July, 2008

6-12-2008 Wall rough-in for water cooler.

 

   June/July, 2008

6-12-2008 Restroom framing on building two.

 

   June/July, 2008

6-16-2008 Grease tramp on the right side of building two.

 

   June/July, 2008

6-16-2008 Grease trap in front of building one.

 

   June/July, 2008

6-16-2008 Man hole in front of building one.

 

   June/July, 2008

6-16-2008 Man hole in front of building two.

 

   June/July, 2008

6-12-2008 Unit B-7.

 

   June/July, 2008

6-16-2008 Running sewer line in front of building one.

 

   June/July, 2008

6-16-2008 Sewer line in front of building two.

 

  June/July, 2008

6-18-2008
Dens Glass on the back side of
building one.

 

  June/July, 2008

6-18-2008
Finish plywood on building two.

 

   June/July, 2008

6-19-2008 Forming up curb and gutter
on the back side of the building.

 

   June/July, 2008

6-19-2008 Grease trap for unit A-1 tie-in.

 

   June/July, 2008

6-19-2008 Grease trap for unit B-6 tie-in.

 

   June/July, 2008

6-19-2008 Left side of building two.

 

   June/July, 2008

6-19-2008 Running plywood and dens glass on
building one right side.

 

   June/July, 2008

6-20-2008 Masonry on building two.

 

   June/July, 2008

6-20-2008 Wall ties on building two.

 

   June/July, 2008

6-21-2008 Masonry complete on dumpster pad behind building one.

 

   June/July, 2008

6-21-2008 Roof on building two.

 

   June/July, 2008

6-21-2008 Tower on building two.

 

   June/July, 2008

6-26-2008 Screen wall for electrical panels.

 

   June/July, 2008

6-30-2008 Running conduit to transformer.

 

  June/July, 2008

6-19-2008
Exterior framing on building one.

 

  June/July, 2008

6-21-2008
Dens glass and plywood complete
on back side of building one.

 

  June/July, 2008

6-21-2008
Felt paper complete on building two.

 

  June/July, 2008

6-21-2008
Fire hydrant behind building two.

 

  June/July, 2008

6-27-2008
Blocking for restroom.

 

  June/July, 2008

6-30-2008
Conduit for TV and Phone.

 

  June/July, 2008

6-30-2008 Running conduit to transformer.JPG

 

  June/July, 2008

6-30-2008 Running conduit between both building.

 

  June/July, 2008

7-16-2008
Curb along the front of both buildings.

 

  June/July, 2008

7-22-2008
Box for fire alarm.

 

  June/July, 2008

7-1-2008 Running conduit down farrow parkway to switch gear.

 

  June/July, 2008

7-3-2008 Laying brick on screen wall for building two.

 

  June/July, 2008

7-8-2008 Poured concrete on dumpster pad
behind building one.

 

  June/July, 2008

7-8-2008 Running stucco on building one.

 

  June/July, 2008

7-8-2008 Stucco on the back side of building two.

 

  June/July, 2008

7-8-2008 Stucco on the right rear corner of building two.

 

  June/July, 2008

7-8-2008 Siding on right front corner of building one.

 

  June/July, 2008

7-8-2008 Siding on right front corner of building two.

 

  June/July, 2008

7-8-2008 Store fronts going in on building one.

 

  June/July, 2008

7-16-2008 Poured side walk along front of building one.

 

  June/July, 2008

77-16-2008 Forming up curb and gutter on
the left rear corner of building one.

 

  June/July, 2008

7-16-2008 Forming up side walk between both building.

 

  June/July, 2008

7-16-2008 Grading for curb along the back
side of building one.

 

  June/July, 2008

7-16-2008 Middle of building two.

 

  June/July, 2008

7-16-2008 Installing wood timber on towers on building two.

 

  June/July, 2008

7-16-2008 Mounting meter center on building two.

 

  June/July, 2008

7-22-2008 Installing grills.

 

  June/July, 2008

7-22-2008 Insulated water lines in restroom.

 

  June/July, 2008

7-24-2008 Pouring side walks in between both building.

 

  June/July, 2008

7-28-2008 Left end on the front of building one.

 

  June/July, 2008

7-28-2008 Left front corner of building one.

 

  June/July, 2008

7-28-2008 Left rear corner of building one.

 

  June/July, 2008

7-28-2008 Right rear corner of building one.

 

  June/July, 2008

7-28-2008 Back right end of building one.

 

  June/July, 2008

7-28-2008 Left front corner of building two.

 

  June/July, 2008

7-28-2008 Right front corner of building two.

 

  June/July, 2008

7-28-2008 Back side of building two.

 

  June/July, 2008

7-28-2008 Left rear corner of building two.

 

  June/July, 2008

7-28-2008 Pulling wire into the unit of building two.

 

  June/July, 2008

7-28-2008 Unit A-1.

 
 

 Feb, 2008    Mar, 2008   April/May, 2008   Additional May, 2008  June/July, 2008   Aug/Sept, 2008

 