Newberry Atrium Upfit
Construction Progress Photos
April, 2008
1. Ceramic Tile at Planter at Front Entrance.
Installing Carpet on Front Stairs.
VCT in suite D1 Room D 110.
Desk in D1 Cardiac Gym.
Toilet Partition in D1 Mens Locker Room.
Handicap Toilet Partition in D1 Men's Locker Room.
Casework in D1 Registration Desk.
Toilet Partitions in 1st Floor Main Restroom.
Casework in Suite B1 Room B117.
Installing Carpet in Suite C1 Room C 100.
Painting West Stairwell.
Installing Carpet in Suite 2 Waiting Room.
Corridor 204 in Suite 2.
Main Stair at Front Entrance.
Nurse Station B 110 in Suite B1.
Corridor B113 in Suite B1
1st Floor Main Corridor.
Classroom D102 in Suite D1.
Office D 130 in Suite D1.
Waiting Room B 200 in Suite B2.
Corridor B 224 in Suite B2.
Casework in Procedure Room B 218 in Suite B2.
Corridor B 221 in Suite 2.
Exam Room 116 in Suite 1.
Chart 111 in Suite 1.
OT 126 in Suite 1.
Top of page
December 2007/January 2008 February, 2008 March, 2008 April, 2008